Tag Archives: Gwynt y Môr

Gwynt y Môr Windfarm: Weekly Progress Report, 24th August 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 24th August 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 24th August 2015

Gwynt y Môr: Diving Operations, August 2015

Mariners are advised that diving operations are due to be carried out at various locations in the Gwynt y Môr Offshore Wind Farm between the 20th and 27th August 2015 from the vessel Channel Chieftain VII.  A notice to mariners … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr: Diving Operations, August 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 17th August 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 17th August 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 17th August 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 2nd August 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 2nd August 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 2nd August 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 27th July 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 27th July 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 27th July 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 9th July 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 9th July 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 9th July 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 26th June 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd June 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 26th June 2015

Gwynt y Môr: Notice to Mariners – Export Cable, June 2015

Mariners are advised that following recent cable maintenance works conducted by Balfour Beatty, a short stretch of cable remains exposed on the seabed.  A Notice to Mariners has been issued to advise of the location of this cable.  This notice can … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr: Notice to Mariners – Export Cable, June 2015

Gwynt y Môr: Export Cable Maintenance Works, June 2015

Mariners are advised that cable maintenance works are due to be carried out on the export cable from the Gwynt y Môr Offshore windfarm from the 17th June 2015 until further notice.  A Notice to Mariners has been issued by Balfour Beatty in … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , | Comments Off on Gwynt y Môr: Export Cable Maintenance Works, June 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 8th June 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th June 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 8th June 2015