Gwynt y Môr Windfarm: Weekly Notice of Operations, 11th May 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Wind Farm issued on 11th May 2012 to harbour masters and sea users .  This notice describes recent operations, work planned for the next 7 days, and provides a list of vessels operating on the site with their contact details.

Work carried out over past 7 days

The following work has been carried out in the past week:

  • Freja has been carrying out survey work on the export cable route (see our earlier update here).
  • Union Boxer towing barge UR 99 and carrying the OSP East Jacket arrived on site on 7th May 2012.
  • Penrhos Bay has been used as a CTV / Stand by vessel, running out of Conwy Marina.  She will stand by during jacket installation duties (see the Notice to Mariners 10 here).
  • Stanislav Yudin commenced work on on the installation of the Sub Station East on the 8th May 2012.
  • Anglian Monarch has been providing support for Stanislav Yudin.
  • Anglian Earl has been providing support for Stanislav Yudin.
  • Union Beaver has completed the work of laying mattresses & carrrying out Diving Operations at various locations alongside workbarge MPR2 who has been assisting with anchors (see earlier update here).

Work planned for next 7 days

The work planned for the next 7 days on the site is:

  • Freja will be carrying out survey work on the export cable route (see earlier update here).
  • Penhros Bay will be utilised as Crew Transfer / Stand by vessel, running out of Conwy Marina. To stand by during Jacket installation duties.
  • Stanislav Yudin will continue installation work (see our previous notice here).
  • Anglian Monarch and Anglian Earl will continue to provide support to Stanislav Yudin.
  • Guard vessel Choice is expected to arrive on site on the 15th May 2012 and commence guard vessel duties in-field.

List of vessels at site for next 7 days

The vessels that will be operating on the site over the next 7 days and their contact details are given below.  We have linked up the vessel names to MarineTraffic.com so that with just one mouse click you can find out more about their current location and recent activity.

  • Freja: Export cable survey vessel | Call sign VSY 07.
  • Penrhos Bay:  Crew transfer vessel | Call sign 2DLB8.
  • Stanislav Yudin: Crane vessel | Call sign 5BYM2 |
  • Anglian Monarch: support vessel for Stanislav Yudin | Call sign MYFR6.
  • Anglian Earl: support vessel for Stanislav Yudin | Call sign 8PRA
  • Union Boxer (tbc): Tug for Delivery Barge | Call sign ORPS
  • Bremen Fighter: Tug for Delivery Barge | Call sign V20Y1.
  • Choice: Marine Mammal Observation Vessel / Guard Vessel.

Port Arrivals

The planned port arrivals over the next 7 days are:-

  • Cammel Laird Birkenhead/Port of Liverpool.
    MV Bente arrived on 8th May 2012 delivering transition pieces and monopiles.
  • Mostyn.
    None planned

Please contact Jim Andrews, Fishery Liaison Officer (+44(0)7908-225865) if you have any queries or concerns about these activities.

This entry was posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm. Bookmark the permalink.