Tag Archives: undersea cable

Gwynt y Môr Export Cable Survey: Update – Repair Works – July & August 2024

[Please note – this work is now complete and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] Mariners are advised that maintenance work is continuing on one of the export cables from … Continue reading

Posted in Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , , , , | Comments Off on Gwynt y Môr Export Cable Survey: Update – Repair Works – July & August 2024

Gwynt y Môr Export Cable Survey: Update – Fault Identification and Preparatory Works – July 2024

[Please note – this work is now complete, the anchors have been recovered, and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] Mariners are advised that maintenance work is due to be … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , , , | Comments Off on Gwynt y Môr Export Cable Survey: Update – Fault Identification and Preparatory Works – July 2024

Gwynt y Môr Export Cable Survey: Update – Anchoring Works – July 2024

[Please note – this work is now complete, the anchors have been recovered, and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] Mariners are advised that pre-construction work is due to be … Continue reading

Posted in Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , , , | Comments Off on Gwynt y Môr Export Cable Survey: Update – Anchoring Works – July 2024

Gwynt y Môr Export Cable Survey: Update – June 2024

[Please note – this survey is now complete and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] Mariners are reminded that a pre-construction survey of the export cable from the Gwynt y … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , , , | Comments Off on Gwynt y Môr Export Cable Survey: Update – June 2024

Gwynt y Môr Offshore Wind Farm: Survey Operations Update, June 2024

[Please note – this survey is now complete and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] Mariners are advised that survey operations are due to be carried out off the North … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , , , , | Comments Off on Gwynt y Môr Offshore Wind Farm: Survey Operations Update, June 2024

Gwynt y Môr Export Cable Survey: Update – May 2024

[Please note – this survey is now complete and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] Mariners are advised that a pre-construction survey of the export cable from the Gwynt y … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , , , | Comments Off on Gwynt y Môr Export Cable Survey: Update – May 2024

Western HVDC Link: Offshore survey work, April-May 2024

[Please note – this survey is now complete and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] Mariners are advised that survey work is due to be carried out along the Western … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link | Tagged , , , , , , , , , , | Comments Off on Western HVDC Link: Offshore survey work, April-May 2024

Moyle Interconnector, Larne and Belfast Lough Crossing Pipelines: Marine Survey Progress Update, October-November 2022

This is a progress report for mariners about the marine geophysical survey work being conducted in the North Channel over both of the Moyle Interconnector Cables and also the Scotland to Northern Ireland Pipeline. This survey work started in September … Continue reading

Posted in Awel y Mor Offshore Wind Farm, AWJ Updates, Fishery Liaison | Tagged , , , , , | Comments Off on Moyle Interconnector, Larne and Belfast Lough Crossing Pipelines: Marine Survey Progress Update, October-November 2022

Gwynt y Môr Export Cable: Survey Operations, April 2022

Mariners are advised that survey operations are due to be carried out off the North Wales coast in the area between Rhyl and the Gwynt y Môr Offshore Wind Farm during April 2022.  A Notice to Mariners has been issued, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , , , , | Comments Off on Gwynt y Môr Export Cable: Survey Operations, April 2022

Western HVDC Link Update: Progress of deep-water survey work, October-November 2021

[Please note – this survey is now complete and the Notice to Mariners has been withdrawn.  This information is retained here for reference purposes only.] This is an update for Mariners on the progress of the survey work that is … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , , , , , , | Comments Off on Western HVDC Link Update: Progress of deep-water survey work, October-November 2021