Category Archives: AWJ Updates

Hunterston – Kintyre Undersea Cable: HDD Landfall, Ardneil Bay

Mariners are advised that on the 9th February 2015, a long plastic pipe (500m long and 560mm in diameter) is due to be towed from Hunterston to Ardneil Bay.  This pipe will then be pulled ashore through a hole that has been … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , | Comments Off on Hunterston – Kintyre Undersea Cable: HDD Landfall, Ardneil Bay

Gwynt y Môr Windfarm: Weekly Progress Report, 25th January 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 25th January 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 25th January 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 18th January 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 18th January 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 18th January 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 11th January 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 11th January 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 11th January 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 4th January 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 4th January 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 4th January 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 29th December 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th December 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 29th December 2014

Gwynt y Môr Windfarm: Weekly Progress Report, 22nd December 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 21st December 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 22nd December 2014

Gwynt y Môr: Current Notices to Mariners

Mariners are advised that there are presently just two Notices to Mariners currently in force for the Gwynt y Môr offshore wind farm.  Information about these notices is presented below. Scour Protection works Scour protection work is within the Gwynt y … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr: Current Notices to Mariners

Update: Mainland – Isle of Jura Electricity Cable

All of the installation and survey work on the cable has now been completed.  The cable was installed an energised on Sunday 7th December 2014, and the survey work along the  cable route was completed on Saturday 13th December 2014.  All … Continue reading

Posted in AWJ Updates, Fishery Liaison, Jura to Mainland Undersea Cable | Tagged , , , | Comments Off on Update: Mainland – Isle of Jura Electricity Cable

Gwynt y Môr: FLIDAR Anchor Buoyage

Mariners are advised that following the removal of the FLIDAR buoy to the east of the Gwynt y Môr windfarm earlier this month, two buoys have been deployed to mark the location of the anchors that remain on the seabed. … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , | Comments Off on Gwynt y Môr: FLIDAR Anchor Buoyage