Gwynt y Môr Windfarm: Weekly Progress Report, 1st October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Offshore Windfarm: Construction Update

Two new activities are due to take place in the Gwynt y Môr Offshore Windfarm area in the next few days.  The new jack up rig, Frederich Ernestine, is due to start trials on site; and a high-tech buoy for … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 24th September 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 24th September 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

PRIORITY NOTICE Gwynt y Môr Windfarm: Navigation hazard 21st September 2012

A Navigation Warning advising of exposed monopiles has been issued for the Gwynt y Môr Offshore Windfarm today, 21st September 2012.  The full notice can be downloaded here and is summarised below. There are now a total of three exposed monopiles within the … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 17th September 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 17th September 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

WHVDC Undersea Cable: Survey Update 14th September 2012

An update on the survey work being carried out for the proposed WHVDC undersea cable has been issued today, 14th September 2012.  A notice to mariners about this work was issued last month and can be downloaded here. Survey update A brief … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

MSC Surveillance Audit: German North Sea Saithe Trawl Fishery

The annual Surveillance Audit for the German North Sea Saithe Trawl Fishery has just been announced on the MSC website. We will be carrying out this audit in partnership with Intertek Moody Marine on the 17th-18th October 2012 at Cuxhaven and Hamburg … Continue reading

Posted in AWJ Updates, MSC Certification, Sustainability | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 10th September 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 10th September 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

PRIORITY NOTICE Gwynt y Môr Windfarm: Navigation hazard 10th September 2012

A Navigation Warning advising of a navigation hazard has been issued for the Gwynt y Môr Offshore Windfarm today, 10th September 2012.  The full notice can be downloaded here and is summarised below. The notice advises that the cable laying barge Cable Enterprise … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

PRIORITY NOTICE Gwynt y Môr Windfarm: Navigation hazards

A Navigation Warning advising of exposed monopiles has been issued for the Gwynt y Môr Offshore Windfarm today, 7th September 2012.  The full notice can be downloaded here and is summarised below. The notice advises that there are exposed monopiles within the … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment