Gwynt y Môr Windfarm: scour protection work

Scour protection work is due to recommence on the Gwynt y Môr Offshore Wind Farm on the 3rd September 2012 and is due to continue until 17th September.

This work is due to be carried out from the vessel Tideway Rollingstone.  A Notice to Mariners providing details of this activity has been published by RWE nPower Renewables and is available for download here.

The contact details for the Tideway Rollingstone are given below, with a link to the vessel details on the MarineTraffic.com website.  You can observe the current location of the vessel and recent movements by following this link.

Terramare 1 will be contactable on VHF Channel 16.

Please contact Jim Andrews, Fishery Liaison Officer by e-mail or phone (+44(0)7908-225865) if you have any queries or concerns about these activities.

This entry was posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm. Bookmark the permalink.