Tag Archives: rock placement

Western HVDC Link Progress Update: September 25th 2017

Mariners are advised that work has recently been completed on the rock protection work to the south of the Isle of Man and the survey work on the Western HVDC Link cable route in the North Channel and Irish Sea.

Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable Tagged , , , , , , , , , ,

Western HVDC Link: Post Lay Installation Rock Placement Works, Ardneil Bay

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable Tagged , , , , , ,

Western HVDC Link: Exposed cable locations, Irish Sea, North Channel, Firth of Clyde

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable Tagged , , , , , , , ,

Western HVDC Link: Deep Water Cable Post Lay Rock Placement Works, 1st February 2017

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable Tagged , , , , , ,

Western HVDC Link: Deep Water Cable Post Lay Installation Burial Works, 23rd November 2016

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable Tagged , , , , , , , ,

Moyle Returns Project: Rock Protection Update, 1st June 2016

This is an update on progress with the rock protection work on the Moyle Returns Cables in the North Channel of the Irish Sea.  A revised Notice to Mariners was issued for this work in October 2015 and can be downloaded Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable Tagged , , , , , ,

Moyle Returns Project: Installation Update, 26th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable Tagged , , , , , ,

Hunterston-Kintyre Cable: Rock placement update, 19th September 2015

This notice provides an update on progress with rock placement work on the Hunterston-Kintyre undersea cable in the Firth of Clyde.

Rock placement work started on the 9th September with the vessels Seahorse and Rockpiper working close to the Kintyre and Hunterston … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable Tagged , , , ,

Moyle Returns Project: Update – nearshore rock placement, Scottish landfall

This notice provides a further update on progress with activities for the rock protection of the nearshore sections of the Moyle Interconnector cables.   This work started recently, and progress is summarised briefly below.

Nearshore Rock Placement, Scottish Landfall

On the … Continue reading

Posted in Fishery Liaison, Moyle Interconnector Cable Tagged , , ,

Moyle Returns Project: Update – nearshore rock placement, September 2015

This notice provides an update on progress with activities for the rock protection of the nearshore sections of the Moyle Interconnector cables.   This work started recently, and progress is summarised briefly below.

Rock Placement

Survey work by the vessel Smit … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable Tagged , , , ,