Scotland to Northern Ireland Pipeline: Subsea Rock Installation, December 2021

Mariners are advised that remediation works are due to be carried out on part of the Scotland to Northern Ireland Pipeline in December 2021.  A Notice to Mariners describing the work can be downloaded here and is summarised below. Timing … Continue reading

Posted in Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , | Comments Off on Scotland to Northern Ireland Pipeline: Subsea Rock Installation, December 2021

Western HVDC Link: Completion of Survey and Rock Placement work, Irish Sea & Firth of Clyde

Mariners are advised that survey work on the Western HVDC link cable in the Irish Sea, North Channel and Firth of Clyde has now been completed.  Rock placement work in the North Channel and Firth of Clyde has also been … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , , , , , , , | Comments Off on Western HVDC Link: Completion of Survey and Rock Placement work, Irish Sea & Firth of Clyde

Western HVDC Link: Rock Placement works, Irish Sea & Firth of Clyde – October 2019

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , , , | Comments Off on Western HVDC Link: Rock Placement works, Irish Sea & Firth of Clyde – October 2019

Western HVDC Link Progress Update: September 25th 2017

Mariners are advised that work has recently been completed on the rock protection work to the south of the Isle of Man and the survey work on the Western HVDC Link cable route in the North Channel and Irish Sea. … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , , , , , | Comments Off on Western HVDC Link Progress Update: September 25th 2017

Western HVDC Link: Post Lay Installation Rock Placement Works, Ardneil Bay

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , | Comments Off on Western HVDC Link: Post Lay Installation Rock Placement Works, Ardneil Bay

Western HVDC Link: Exposed cable locations, Irish Sea, North Channel, Firth of Clyde

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , , , | Comments Off on Western HVDC Link: Exposed cable locations, Irish Sea, North Channel, Firth of Clyde

Western HVDC Link: Deep Water Cable Post Lay Rock Placement Works, 1st February 2017

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , | Comments Off on Western HVDC Link: Deep Water Cable Post Lay Rock Placement Works, 1st February 2017

Western HVDC Link: Deep Water Cable Post Lay Installation Burial Works, 23rd November 2016

[Update – the information in this notice has been superseded by more recent notices.  The notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , , , , , | Comments Off on Western HVDC Link: Deep Water Cable Post Lay Installation Burial Works, 23rd November 2016

Moyle Returns Project: Rock Protection Update, 1st June 2016

This is an update on progress with the rock protection work on the Moyle Returns Cables in the North Channel of the Irish Sea.  A revised Notice to Mariners was issued for this work in October 2015 and can be downloaded here, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , , | Comments Off on Moyle Returns Project: Rock Protection Update, 1st June 2016

Moyle Returns Project: Installation Update, 26th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , , | Comments Off on Moyle Returns Project: Installation Update, 26th October 2015