Navigation Update: Survey of Export Cable

Survey work on the export cable from the Gwynt y Môr Offshore Windfarm is due to start imminently.  A notice about these operations can be downloaded here and is summarised below.

The survey of Subsea Export Cable No. 1 is due to start on Wednesday 13th March 2013 for approximately 1 week.  The survey work will be carried out by the survey vessel Lia, which will be working in the approximate position 53°11’N  03°36’W.

MV Lia will be towing survey equipment from her stern.  Vessels are asked to observe a 500m safety zone around the Lia.  The call sign for the Lia and also a link to information about the vessel, is given below.

  • Lia: survey vessel | Call sign MERD8

Please contact Jim Andrews, Fishery Liaison Officer by e-mail or phone (+44(0)7908-225865) if you have any queries or concerns about this notice.

This entry was posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm. Bookmark the permalink.