Our Latest News
- Awel y Môr Offshore Wind Farm Export Cable Route: Geotechnical Survey Operations, June 2026
Mariners are advised that geotechnical survey…
- Awel y Môr Offshore Wind Farm: Update on Geotechnical Survey Operations, May-June 2026
This is an update on our earlier Notice to…
- Awel y Môr Offshore Wind Farm: Geophysical Survey Operations, May-July 2026
Mariners are advised that geophysical survey…
- Awel y Môr Offshore Wind Farm: Geotechnical Survey Operations, May-June 2026
Mariners are advised that geotechnical survey…
- Rhyl Flats Offshore Wind Farm: Update on Heavy Lift Operations, April 2026
This is an update to mariners about the timetable…
- Awel y Môr Offshore Wind Farm Export Cable Route: Geotechnical Survey Operations, June 2026
Tag Archives: windfarm
Gwynt y Môr Windfarm: Weekly Progress Report, 15th March 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th March 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 15th March 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 8th March 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th March 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 8th March 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 1st March 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st March 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 1st March 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 22nd February 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd February 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 22nd February 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 15th February 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th February 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 15th February 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 8th February 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th February 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 8th February 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 25th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 25th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 25th January 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 18th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 18th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 18th January 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 11th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 11th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 11th January 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 4th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 4th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 4th January 2015