Our Latest News
- Rhyl Flats Offshore Wind Farm: Update on Heavy Lift Operations, March-April 2026
Mariners are advised of a change to the…
- North Hoyle Offshore Wind Farm: Heavy Lift Operations, March-April 2026
Mariners are advised that the jack up vessel MPI…
- Rhyl Flats Offshore Wind Farm: Heavy Lift Operations, March-April 2026
[The information below has been superceded by a…
- Gwynt y Môr Offshore Wind Farm: Heavy Lift Operations, March 2026
Mariners are advised that maintenance operations…
- Gwynt y Môr Offshore Wind Farm: Survey Operations, February 2026
Mariners are advised that survey operations are…
- Rhyl Flats Offshore Wind Farm: Update on Heavy Lift Operations, March-April 2026
Tag Archives: notice to mariners
Gwynt y Môr: Scour Protection work, November 2014
Mariners are advised that the rock dumping vessel Seahorse will be commencing operations at various locations within and around the Gwynt y Môr Offshore Wind Farm in late November 2014 until further notice. A Notice to Mariners about this work … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr: Scour Protection work, November 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 17th November 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 16th November 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 17th November 2014
Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, November 2014
Mariners are advised that the first cable laying campaign for the Western HVDC Link has been successfully completed in Liverpool Bay. A Notice to Mariners advising of progress, the extent of the cable that has been laid, and the location … Continue reading
Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable
Tagged construction update, notice to mariners, undersea cable, Western HVDC Link
Comments Off on Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, November 2014
Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands
Mariners are advised that operations for the Western HVDC landfall at Ardneil will commence during the week commencing 10th November 2014. A Notice to Mariners advising about the timetable for operations can be downloaded here and is summarised below. The previous Notice … Continue reading
Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable
Tagged construction update, notice to mariners, undersea cable, Western HVDC Link
Comments Off on Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands
Gwynt y Môr Windfarm: Weekly Progress Report, 9th November 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 9th November 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 9th November 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 3rd November 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 2nd November 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 3rd November 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 27th October 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 27th October 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 27th October 2014
Western HVDC Link Update: Notice to Mariners
A Notice to Mariners has been issued today by the Port of Liverpool advising of some areas of exposed cable in Liverpool Bay. This cable will from part of the Western HVDC Link undersea electricity cable. The full notice can … Continue reading
Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable
Tagged construction update, notice to mariners, undersea cable, Western HVDC Link
Comments Off on Western HVDC Link Update: Notice to Mariners
Gwynt y Môr Windfarm: Weekly Progress Report, 19th October 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 19th October 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 19th October 2014
Gwynt y Môr: Notice to Anglers
From the 1st October 2014, angling vessels will be able to re-commence fishing within the Gwynt y Môr Offshore Wind Farm Site. Although construction work is still continuing on the site, the level of activity is such that angling activities … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr: Notice to Anglers