- Western HVDC Link: Geophysical Survey Operations, December 2025
Mariners are advised that survey work is due to…
- Gwynt y Môr Offshore Wind Farm: Maintenance Operations, December 2025
This is an update for mariners about the…
- Maintenance Operations: Rhyl Flats Offshore Windfarm, November-December 2025
Mariners are advised that the jack up vessel MPI…
- Gwynt y Môr Offshore Wind Farm: Survey Operations, November 2025
Mariners are advised that survey operations are…
- Gwynt y Môr Offshore Wind Farm: Survey Operations, October 2025
Mariners are advised that survey operations are…
- Western HVDC Link: Geophysical Survey Operations, December 2025
Tag Archives: Gwynt y Môr
Gwynt y Môr Windfarm: Weekly Progress Report, 18th August 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 18th August 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 18th August 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 11th August 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 11th August 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 11th August 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 4th August 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 4th August 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 4th August 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 28th July 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 28th July 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 28th July 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 21st July 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 21st July 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 21st July 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 14th July 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 14th July 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 14th July 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 7th July 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 7th July 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 7th July 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 30th June 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 30th June 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 30th June 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 16th June 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 16th June 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, UXO, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 16th June 2014
Gwynt y Môr Windfarm: Weekly Progress Report, 9th June 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 9th June 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading