- Our Latest News- Gwynt y Môr Offshore Wind Farm: Survey Operations, October 2025Mariners are advised that survey operations are… 
- Gwynt y Môr Offshore Wind Farm: Update on Jack up Vessel Operations - September 2025[Please note - this work is now complete and the… 
- Update - Gwynt y Môr Export Cable Repair: Replacement operations, September 2025[Please note - this work is now complete and the… 
- Update - Gwynt y Môr Export Cable Repair: Replacement operations, August-September 2025[Please note - this work is now complete and the… 
- Gwynt y Môr Offshore Wind Farm: Jack up Vessel Operations - August 2025[Please note - this work is now complete and the… 
 
- Gwynt y Môr Offshore Wind Farm: Survey Operations, October 2025
Tag Archives: Gwynt y Môr
Gwynt y Môr Windfarm: Weekly Progress Report, 1st March 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st March 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 1st March 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 22nd February 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd February 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 22nd February 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 15th February 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th February 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 15th February 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 8th February 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th February 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 8th February 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 25th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 25th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 25th January 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 18th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 18th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 18th January 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 11th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 11th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 11th January 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 4th January 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 4th January 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 4th January 2015
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 29th December 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th December 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 29th December 2014
							
		Gwynt y Môr Windfarm: Weekly Progress Report, 22nd December 2014
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 21st December 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
									
						Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm					
					
				
								
					Tagged construction update, Gwynt y Môr, notice to mariners, windfarm				
				
				
				Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 22nd December 2014
							
		