- Rhyl Flats Offshore Wind Farm: Heavy Lift Operations, March-April 2026
Mariners are advised that the jack up vessel MPI…
- Gwynt y Môr Offshore Wind Farm: Heavy Lift Operations, March 2026
Mariners are advised that maintenance operations…
- Gwynt y Môr Offshore Wind Farm: Survey Operations, February 2026
Mariners are advised that survey operations are…
- Western HVDC Link: Geophysical Survey Operations, December 2025
[Please note – this work is now complete and…
- Gwynt y Môr Offshore Wind Farm: Maintenance Operations, December 2025
This is an update for mariners about the…
- Rhyl Flats Offshore Wind Farm: Heavy Lift Operations, March-April 2026
Category Archives: AWJ Updates
Western Link Power Cable: Wirral installation due to commence
Work on the installation of the Wirral end of the Western Link undersea power cable is due to commence in July 2013. A Notice to Mariners has been issued about this work and can be downloaded here. We have summarised the … Continue reading
Gwynt y Môr Windfarm: navigation warning about installation of monitoring buoys
A Floating Light Detection and Ranging (FLIDAR) buoy together with a Wave Rider Buoy (WRB) are due to be installed in the vicinity of Gwynt y Môr windfarm during early-mid July 2013. A Navigation Warning about the installation of these … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 8th July 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th July 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 1st July 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st July 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Sea Worker to start wind turbine installation.
On June 26th 2013 the jack up rig Sea Worker will commence Wind Turbine Generator (WTG) installation works at the Gwynt y Môr Offshore Wind Farm. The Sea Worker will be towed from the Port of Mostyn to the wind farm on a … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 24th June 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 24th June 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 17th June 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 17th June 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 10th June 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 10th June 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Arrival of Accommodation Vessel “Wind Solution”
On June 5th 2013 the accommodation vessel Wind Solution is due to arrive in the vicinity of the Gwynt y Môr Offshore Wind Farm. The vessel will be anchored inshore of the wind farm. Further information is provided in the Notice … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 3rd June 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 3rd June 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading