Category Archives: Moyle Interconnector Cable

Moyle Returns Project: Rock Protection Update, 15th December 2015

This is an update on progress with the rock protection work on the Moyle Returns Cables in the North Channel of the Irish Sea.  A revised Notice to Mariners was issued for this work in October and can be downloaded here, giving … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , | Comments Off on Moyle Returns Project: Rock Protection Update, 15th December 2015

Moyle Returns Project: Rock Protection Update, December 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A revised Notice to Mariners was issued for this work in October and can be downloaded here, giving up-to-date … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , | Comments Off on Moyle Returns Project: Rock Protection Update, December 2015

Moyle Returns Project: Installation Update, 26th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , , | Comments Off on Moyle Returns Project: Installation Update, 26th October 2015

Moyle Returns Project: Installation Update, 12th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , | Comments Off on Moyle Returns Project: Installation Update, 12th October 2015

Moyle Returns Project: Update – nearshore rock placement, Scottish landfall

This notice provides a further update on progress with activities for the rock protection of the nearshore sections of the Moyle Interconnector cables.   This work started recently, and progress is summarised briefly below. Nearshore Rock Placement, Scottish Landfall On the … Continue reading

Posted in Fishery Liaison, Moyle Interconnector Cable | Tagged , , , | Comments Off on Moyle Returns Project: Update – nearshore rock placement, Scottish landfall

Moyle Returns Project: Update – nearshore rock placement, September 2015

This notice provides an update on progress with activities for the rock protection of the nearshore sections of the Moyle Interconnector cables.   This work started recently, and progress is summarised briefly below. Rock Placement Survey work by the vessel Smit … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , | Comments Off on Moyle Returns Project: Update – nearshore rock placement, September 2015

Moyle Returns Project: Update – nearshore rock placement, September 2015

This notice provides an update on progress with activities for the rock protection of the nearshore sections of the Moyle Interconnector cables.   This work is due to commence shortly, and is summarised briefly below. Nearshore Rock Placement Survey work … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , | Comments Off on Moyle Returns Project: Update – nearshore rock placement, September 2015

Moyle Returns Project: Notice to Mariners: Rock Placement, September 2015

Mariners are advised that rock placement work on the Moyle Interconnector cables is due to start in September 2015.  A Notice to Mariners has been issued for this work, detailing the schedule of work.  This notice can be downloaded here and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , | Comments Off on Moyle Returns Project: Notice to Mariners: Rock Placement, September 2015

Moyle Returns Project: Installation Update, 14th August 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has been issued for this work, detailing the route and construction schedule.  This notice … Continue reading

Posted in Fishery Liaison, Moyle Interconnector Cable | Tagged , , , | Comments Off on Moyle Returns Project: Installation Update, 14th August 2015

Moyle Returns Project: Notice to Mariners, July 2015

Mariners are advised that work on the repair of the Moyle Interconnector cables is due to start on the 1st August 2015.  A Notice to Mariners has been issued for this work, detailing the route and construction schedule.  This notice can … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , | Comments Off on Moyle Returns Project: Notice to Mariners, July 2015