Category Archives: Gwynt y Môr Offshore Wind Farm

Gwynt y Môr Windfarm: Weekly Progress Report, 29th October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 22nd October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 15th October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Navigation Hazard Removed

Mariners and sea users are advised that the vessel Cable Enterprise has now recovered the cable plough that has been in wet store off the North Wales coast.  Gwynt y Môr Windfarm Navigation Warning 002 (dated 10th September 2012 and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 8th October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

PRIORITY NOTICE Gwynt y Môr Windfarm 8th October 2012: Additional Navigation hazard

A further Navigation Warning advising of Transition Pieces and monopiles with unlit navigation beacons has been issued for the Gwynt y Môr Offshore Windfarm today, 8th October 2012.  The full notice can be downloaded here and is summarised below. There are currently fourteen (14) … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

PRIORITY NOTICE Gwynt y Môr Windfarm: Navigation hazard 5th October 2012

A Navigation Warning advising of Transition Pieces with unlit navigation beacons has been issued for the Gwynt y Môr Offshore Windfarm today, 5th October 2012.  The full notice can be downloaded here and is summarised below. There are eleven (11) potential hazards within … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

PRIORITY NOTICE Gwynt y Môr Windfarm: Navigation hazard 2nd October 2012

A Navigation Warning advising of Transition Pieces with unlit navigation beacons has been issued for the Gwynt y Môr Offshore Windfarm today, 2nd October 2012.  The full notice can be downloaded here and is summarised below. There are three (3) transition pieces within … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 1st October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Offshore Windfarm: Construction Update

Two new activities are due to take place in the Gwynt y Môr Offshore Windfarm area in the next few days.  The new jack up rig, Frederich Ernestine, is due to start trials on site; and a high-tech buoy for … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment