Our Latest News
- Gwynt y Môr Offshore Wind Farm: Update on Jack up Vessel Operations - September 2025
This is an update for mariners about the…
- Update - Gwynt y Môr Export Cable Repair: Replacement operations, September 2025
This is an update for mariners about the cable…
- Update - Gwynt y Môr Export Cable Repair: Replacement operations, August-September 2025
This is an update for mariners about the cable…
- Gwynt y Môr Offshore Wind Farm: Jack up Vessel Operations - August 2025
[Please note that most of this work has now been…
- Maintenance Operations: North Hoyle and Rhyl Flats Offshore Windfarms, July - August 2025
[Please note - this work is now complete and the…
- Gwynt y Môr Offshore Wind Farm: Update on Jack up Vessel Operations - September 2025
Category Archives: Gwynt y Môr Offshore Wind Farm
Gwynt y Môr Windfarm: Weekly Progress Report, 27th January 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 27th January 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Notice to Mariners – Cable Installation Update
A Notice to Mariners about the inter-array cable installation work at Gwynt y Môr Offshore Wind Farm has just been issued. The notice is summarised below and can be downloaded here. Inter Array Cable Installation Work The cable laying vessel Sia … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 20th January 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 20th January 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 13th January 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 13th January 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 6th January 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 6th January 2014 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Notice to Mariners – Construction Update
Notices to Mariners about the construction activity scheduled for Gwynt y Môr Offshore Wind Farm during 2014 have been issued. These notices are summarised below. 1. Construction work update for 2014 Operations at the wind farm will continue into 2014. … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 29th December 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th December 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 23rd December 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 23rd December 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 16th December 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 16th December 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 9th December 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 9th December 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading