Gwynt y Môr Windfarm: Weekly Progress Report, 19th November 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 19th November 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 12th November 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 12th November 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 5th November 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 5th November 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Project Update #4

A newsletter detailing progress with the construction of the Gwynt y Môr website has just been published.  You can download a copy here, and we’ve summarised the key points below:-  Offshore More than 40 turbine foundations have now been installed … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 29th October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 22nd October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

MSC Assessment: Falkland Islands Toothfish Longline Fishery

We are delighted to be working with Intertek Moody Marine on the first MSC fishery assessment of a fishery on the Falkland Islands. The site visit for the Falkland Islands Toothfish Longline Fishery is due to take place between the … Continue reading

Posted in AWJ Updates, MSC Certification, Sustainability | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 15th October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Navigation Hazard Removed

Mariners and sea users are advised that the vessel Cable Enterprise has now recovered the cable plough that has been in wet store off the North Wales coast.  Gwynt y Môr Windfarm Navigation Warning 002 (dated 10th September 2012 and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 8th October 2012

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th October 2012 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment