- Gwynt y Môr Offshore Wind Farm: Survey Operations, October 2025
Mariners are advised that survey operations are…
- Gwynt y Môr Offshore Wind Farm: Update on Jack up Vessel Operations - September 2025
[Please note - this work is now complete and the…
- Update - Gwynt y Môr Export Cable Repair: Replacement operations, September 2025
[Please note - this work is now complete and the…
- Update - Gwynt y Môr Export Cable Repair: Replacement operations, August-September 2025
[Please note - this work is now complete and the…
- Gwynt y Môr Offshore Wind Farm: Jack up Vessel Operations - August 2025
[Please note - this work is now complete and the…
- Gwynt y Môr Offshore Wind Farm: Survey Operations, October 2025
Author Archives: Jim Andrews
Western Link: Proposed Survey & Cable Installation Update
A notice to mariners advising of survey work on the proposed Western Link undersea power cable during September 2013 has just been published, and progress is being made with the installation of cable sleeve pipes at the Wirral landfall of … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 2nd September 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 2nd September 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Notice to Mariners – South Stack to commence diving operations
On the 29th August 2013 the vessel South Stack is due to begin diving operations at various turbine locations until further notice. A Notice to Mariners about these operations can be downloaded here and is summarised below. South Stack is a 15m crew transfer vessel and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 26th August 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 26th August 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Western Link Power Cable: Notice to Mariners and Cable Installation Update
Work on the installation of the Wirral end of the Western Link undersea power cable is due to continue in August 2013. A further Notice to Mariners has been issued and can be downloaded here. We have summarised this notice and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 19th August 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 19th August 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 12th August 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 12th August 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 5th August 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 5th August 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Notice to Mariners – Jack up vessel JB114 to commence drilling work
On the 4th August 2013 the jack-up vessel JB-114 is due to begin drilling operations to assist monopile installation in the Gwynt y Môr Offshore Windfarm, until further notice. A Notice to Mariners about these operations can be downloaded here and is summarised below. … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 29th July 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th July 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading