Gywnt Y Môr windfarm: Update on Scour Protection Works

Further to our update of last Friday, please find attached a map of the proposed scour protection work being carried out by Tideway Rollingstone over the next few weeks.

The number of sites has been increased to 45.  Their location is shown in the attached map, and the coordinates (Lat-Long) of each site is in the attached table.  This campaign of work will now last until mid-April.

All vessels are advised that the Tideway Rollingstone will be monitoring VHF Channel 16.  The vessel is dynamically positioned.  All other vessels are advised to keep at least 500m clear.

If you have any queries about these operations, please get in touch.

This entry was posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm. Bookmark the permalink.