This is an update to previous notices advising Mariners about survey work being carried out along part of the Western HVDC Link cable route. The survey work started in October and is due to continue through the rest of November 2026. The survey is being conducted by two XOCEAN Uncrewed Survey Vessels (USVs), the X-08 Uncrewed and X-16 Uncrewed.
An updated Notice to Mariners detailing these operations is summarised below and can be downloaded here.
Survey Work
XOCEAN will undertake a geophysical inspection survey of approximately 127km of the Western Link HVDC cable system from the south of the Isle of Man to its landfall at the Wirral, England.
The survey will be completed using two XOCEAN Uncrewed Surface Vessels (USV) equipped with Multibeam Echo Sounder (MBES) and towed Side Scan Sonar (SSS) systems.
The objective of the survey is to monitor cable burial status, seabed mobility, rock berms, concrete mattresses, cable crossings and associated seabed features identified during previous inspection campaigns
The location of the survey work is illustrated in a map in the Notice to Mariners that can be downloaded here.
Timing
The operations are currently underway and are due to be completed by the 30th of November 2026. The completion date is subject to weather and sea conditions over this period.
Vessel details
The XOCEAN USVs measure 4.5m LOA, with a beam of 2.2m. The USVs are equipped with the following to make them conspicuous to other marine traffic:-
- AIS
- VHF
- Navigation Lights & Sound Signal
- Active Radar Reflector
- Active monitoring from XOCEAN Operations Centre (XOC)
- Superstructure Painted Yellow
- Support vessel assistance when required
The USVs send real time images and situational awareness data over satellite to a team of operators keeping watch and controlling the vessel remotely 24/7. Seafarers are asked to avoid contact with the USVs and be aware of the operational area during this period.
Details of the USVs and a link to their current locations are provided below:
The USVs’ operations will be supported by a crewed Support Vessel, the MV Gallows Point. The support vessel will assist with navigating port limits and be on call to assist and potentially tow, in the unlikely event of a technical failure. The vessel will be based in the operational Beaumaris Port for the duration of survey activities and will be used for the following purposes:
- Providing an escort for the USV to exit and enter the harbour or port
- Assistance with manoeuvring in congested / heavily trafficked locations
- Site reconnaissance, checking for presence of fishing gear etc
- Carry out a tow of the USV back into port in the event of an emergency/technical issue
Details of the support vessel including a link to its current location are provided below:
- MV Gallows Point: support vessel | 16m LOA | Call sign 2BSR9