Mariners are advised that diving and Remotely Operated Vehicle (ROV) operations are due to be carried out at locations along the two high pressure gas interconnector pipelines running between Scotland, Ireland and the Isle of Man during October and December 2026.
A Notice to Mariners describing these operations be downloaded here and is summarised below.
Diving and ROV operations
The survey vessel Aquarius G will be conducting diving operations at the Isle of Man “Tee” pipeline junction and then conducted Remotely Operated Vehicle (ROV) survey and maintenance interventions to remove any debris found across the pipeline. This work is due to start on the 13th of October 2026 and is due to be completed by the 5th of December 2026. The proposed schedule of the survey work is:-
- Diving operations, Isle of Man Tee: 13th October – 15th November 2026
- IC1 Pipeline ROV survey: 7th-12th November 2026
- IC2 Pipeline ROV survey: 19th-23rd November 2026
- Maintenance Operations (as necessary): 30th November – 5th December 2026
All dates are subject to sea and weather conditions. All works are expected to be completed by the 15th of December 2026 at the latest. Updates on progress and changes to the schedule will be provided as the survey progresses.
A map of the pipeline routes with access to downloadable coordinates is available on the Kingfisher Bulletin website here.
Vessel details
The survey will be carried out by N-Sea Aquarius G, which is an Offshore Support Vessel measuring 68m in length and 14.95m beam with a blue hull and white superstructure. Information about the location of the survey vessel can be found at the Marine Traffic website using the link below:-
- N-Sea Aquarius G: Offshore Support Vessel | Call Sign PIPS
The survey vessel will be displaying the relevant day shapes and night lights as specified by the International Regulations for the Prevention of Collisions at Sea (“IRPCS”), and will be monitoring VHF Channels 16 and 12.
The vessel involved in this work may be restricted in its ability to manoeuvre and will be towing gear with a large layback (200-500m). Other vessels are kindly requested to pass at a safe speed and maintain a wide berth of at least 1000m distance to ensure safe navigation.
Further details about the survey vessel are given in the Notice to Mariners which can be downloaded here.
Additional information
The two Irish Sea Gas Interconnectors (“IC1” and “IC2”)are operated by Gas Networks Ireland (“GNI”). A map of the GNI gas pipeline network is available here. The two Irish Sea Interconnectors and the Isle of Man Spur were installed between 1992 and 2003.
GNI have produced a High Pressure Subsea Gas Pipeline Awareness leaflet (available here). This leaflet shows the route of the pipelines, describes their structure and presents advice on hazards associated with them.
Notices to Mariners
Mariners are advised that the following Notices to Mariners have been issued for the survey work along the GNI pipelines and remain current:-
- Irish Sea Gas Interconnector: Offshore Survey, September – October 2026 – this notice was issued in September 2026. It advises mariners that the vessel N-Sea Pathfinder is due to conduct survey operations along the GNI pipelines connecting Scotland, Ireland and the Isle of Man during September and October 2026. A summary of the survey operations and a link to the Notice to Mariners can be accessed here.
All other Notices to Mariners have been withdrawn.